Wednesday, 30 March
Reading the IEA Generation Cost Study
The IEA released the 2010 Edition of the Electricity Generation Cost study:
"Projected Costs of Generating Electricity". There is interesting
information in the Report. One thing of particular interest is the comparison
between countries in terms if the generation mix and the prices. Thanks to the
availability of low-price high-quality coal, Australia remains a low-cost-generating
country.
In terms of projections for the future, the study has to make number of assumptions.
In contrast to the earlier issues in this series, this time the IEA included
the cost of carbon in the projected costs. To do that, they had to make assumptions
about the penalties associated with carbon emissions and the cost of implementing
carbon capture technologies. A carbon price of 30 USD per tonne of CO2 is assumed
to be a likely impost for plants being commissioned in 2015. Carbon capture
costs are baded on what is provided from the participating countries. Only carbon
capture at plant level [CC(S)] is considered. The study uses unproven estimates
on transport and storage to assume that they might add another USD 10-15 per
MWh. Typically, carbon emissions are around 100 tCO2/TJ for hard coal and 50
tCO2/TJ for gas. With standard electric conversion factors of 40% and 55%, this
amounts to emissions of 0.9 tCO2/MWh for electricity from hard coal and of 0.33
tCO2/MWh for electricity from gas-fired power generation. So the inclusion of
the carbon cost makes a significant difference.
In this blog, I try to take down some notes while reading the Report. The following
is not a comprehensive summary and those interested can purchase a copy of the
report from the IEA web
site.
Capital investment costs
The following table summarises the overnight construction costs for different
generation technologies considered in the study. The overnight construction
cost does not consider the discount rate during the time of construction. This
has been included in the study while calculating the levelised costs.
| Type of Plant |
Overnight construction costs |
| Coal without carbon capture |
900-2800 USD/kWe |
Coal with carbon capture at the plant but excluding the cost
of CO2 transport and storage
(the report panel believes that CO2 transport and storage might
add another USD 10-15 per MWh) |
3223-6268 USD/kWe |
| Gas without carbon capture |
520-1800 USD/kWe |
| Nuclear |
1600-5900 USD/kWe |
| Onshore wind |
1900-3700 USD/kWe |
| |
|
The geothermal cost input to the study varied in submissions from different
countries. Well-drilling makes up a large share of the overnight costs of geothermal
electricity generation, sometimes accounting for as much as one-third to one-half
of the total cost of a geothermal project. Capital costs are site-specific,
varying significantly with the characteristics of the local resource system
and reservoir. The overnight construction costs vary from 1 752 USD/kWe in the
United States (for a 50 MWe project) to 12 887 USD/kWe in the Czech Republic
(5 MWe). In the Australian submission (which was made by ESAA), the reported
figure of 4 095 USD/kWe (500 MWe) is said to be on the lower end of construction
costs that can exceed 6700 USD/kWe.
Levelised electricity costs
In calculating the levelised costs, one also needs to make an assumption on
the cost of the fuel, the plant life, the capacity factor, and the decommissioning
costs if any. The study assumed a capacity factor of 85% for nuclear, coal and
gas plants. This assumption is believed to be the upper limit of what is technically
feasible for these technologies.
Government policies and subsidies are not included in the costing.
The Fuel Cost
The study used the price assumptions provided by the IEA Office of the Chief
Economist:
| Hard Coal |
USD90/tonne(USD3.60/GJ) |
| Brown Coal |
Different for different countries |
| Natural Gas |
USD9.76/GJ in OECD Europe
USD11.09/GJ in OECD Asia |
For three OECD countries (Australia, USA and Mexico) and the four non-OECD
countries included in the study, instead of the above table, the specific national
coal and gas prices were used as shown in the following table (the units are
as above):
| Country |
Hard Coal Price, USD/GJ
|
Gas Price, USD/GJ
|
| Australia |
26.65(1.25)
|
7.58
|
| Mexico |
87.50(3.32)
|
7.5
|
| USA |
47.60(2.12)
|
7.4
|
| Brazil |
33.09(1.85)
|
7.71
|
| China |
86.34(2.95)
|
4.53
|
| Russia |
78.00(2.66)
|
5.97
|
| South Africa |
14.63(0.82)
|
|
| |
|
|
For nuclear power plants, the following costs were used: (a) USD1.94/GJ for
the front-end nuclear fuel cycle; and (b) USD0.65/GJ for waste fuel processing
and storage/disposal.
Carbon Price
A carbon price of USD30 per tonne of CO2 was used for the OECD countries; no
carbon price was used for the non-OECD countries.
Plant Life
The expected life was different for different technologies as shown in the
following table:
| Wave and Tidal |
20 |
| Wind and Solar |
25 |
| Gas |
30 |
| Coal |
40 |
| Geothermal |
40 |
| Nuclear |
60 |
| Hydro |
80 |
Decommissioning costs and Residual Value
Where no country data were submitted, the following was used for decommissioning
costs: 15% of the construction costs for nuclear; and 5% of the construction
costs for other technologies.
Construction period
The default assumptions were 1 year for non-hydro renewables; 2 years for gas;
4 years for coal; and 7 years for nuclear power plants. There was no specific
mention for geothermal in this section but the country submissions may have
included the data for geothermal plants so that default assumptions would not
be used in the case of geothermal.
RESULTS
The levelised costs of electricity are calculated based on the above assumptions
and they are presented in the Report for two discount rate scenarios: 5% and
10%. The technologies with a higher capital cost (e.g. nuclear)suffer as the
discount rate is increased. The following two figures displays the regional
levelised costs for nuclear, coal, gas and onshore wind plants.
|
|
|
|
Regional ranges of LCOE for nuclear, coal, gas and onshore
wind power plants (at 5% discount rate)
|
Regional ranges of LCOE for nuclear, coal, gas and onshore
wind power plants (at 10% discount rate)
|
The above graphs do not include renewables other than wind neither it does
include the projected costs for geothermal. These are included in a very detailed
submission by the ESAA on behalf of the Australien electricity generation industry.
In the ESAA submission the cheapest source of electricity when the carbon
costs are included is geothermal energy.
Click here for the rest of the blog